Refurbishment Quay 4, Wismar

Client
MV Werften Wismar Property GmbH
Wendorfer Weg 5
23966 Wismar
Services
Civil and hydraulic engineering
Architect
Union of Architects and Engineers Stralsund GmbH
Project volume
approx. € 20 million

Das Projekt

Depenbrock was awarded the contract to refurbish quay 4 at MV Werften Wismar following a special proposal.

The refurbishment was necessary to prepare the facilities and infrastructure for the final outfitting of the Global Class ships. With their dimensions of 342 m long, 46 m wide and 74 m high, the world’s largest cruise ships place new demands on the shipyard’s infrastructure. The high crane loads in particular require a robust quay construction, which must, however, incorporate the sensitive existing structure.

Quay 4, for example, is being renovated over a length of 460 meters. Extensive test pile driving and noise protection measurements were carried out in preparation. The technical processing and preparation of the structural analysis was carried out by our in-house technical office.